Saving Renfrew's Victory Baths is now expected to cost £910,000 for the planned repairs alone, up from an earlier estimate of £600,000, and that sum does not yet cover the storm-damaged roof above the pool.
Councillors on Renfrewshire Council's Finance, Resources and Customer Services Policy Board met on Thursday 19 November and gave officers the go-ahead to award the repair contract to Clark Contracts Limited. The award still depends on the extra money being approved and on an assessment of the damage caused by Storm Boelo.
Where the money is going
Clark Contracts' tender came in at £672,457.07 before VAT, which was already more than the original budget. Adding a 15% contingency for unexpected work takes the authorised contract to £773,325.63 before VAT, and the £910,000 total also includes professional fees. Officers are asking for an additional £310,000 on top of the £500,000 from the Renfrew Common Good Fund and £100,000 from the council's Financial Sustainability Fund agreed in June 2025.
The council's tender notice, published in June, lists concrete repairs to columns, walls and soffits in the basement, work on the offices and changing areas including ceilings, walls and new flooring, and fixes to the outside ramp. The contract is pencilled in to run from 18 January to 30 April 2027, though that could change once the roof has been looked at.
What happens next
Finance and resources director Alastair MacArthur told the board the damaged section of roof is hard to reach and that he expected it to be assessed within days. The council is working with OneRen, which insures the building, and he said some of the weather-related costs should be met by insurance. Councillor Alison Ann-Dowling pressed for a long-term plan for running and funding the baths, while Councillor Graeme Clark drew comparisons with rising costs at Paisley Museum.
A further report will come back to the board once the cost of the roof repair is known. That leaves swimmers who use the pool still waiting for a clear timetable. The baths were shut after the storm damage, as we reported earlier this month.
Opened in 1921 and designed by Paisley architect Thomas Graham Abercrombie, the Category B listed building still has its 25-yard pool, spectators' gallery and original poolside cubicles.
Originally reported by Renfrewshire News. Tender details from Public Contracts Scotland.